TenderSURE project in Majestic: 6 more months of hell to go; Work in progress meets delay

BBMP's TenderSURE project worth Rs 26 crore in Majestic area has been met with delays due to permissions by the traffic department, officials said. The project will now to take another six months to complete.

First Published Aug 29, 2019, 3:22 PM IST | Last Updated Aug 29, 2019, 3:22 PM IST

 Motorists travelling though Majestic area will have to continue to face issues like increasing pollution, getting stuck in traffic and riding on pothole-filled roads as BBMP's Rs 26 crore worth TenderSURE project has been met with delays.

The chief engineer of projects, Basavaraj Kabade said the traffic department delayed in giving permission for digging of roads and laying of pipes and this has pushed project completion from October to March.