According to a 2018 order of the high court, there exists a "total freeze" on the destruction of mangroves across the state and permission has to be sought from the high court each time an authority wishes to fell mangroves for any public project.

Around 20,000 mangrove trees to be cut for Mumbai-Ahmedabad bullet train project; Bombay HC gives go ahead AJR
Author
First Published Dec 9, 2022, 11:56 AM IST

The Bombay High Court on Friday (December 9) permitted the National High Speed Rail Corporation (NHSRCL) to cut over 20,000 mangrove trees in the city and neighbouring districts of Palghar and Thane for the Mumbai-Ahmedabad bullet train project.

A bench,  headed by Chief Justice Dipankar Datta and Justice Abhay Ahuja allowed the plea filed by the NHSRCL seeking permission to cut the mangrove trees.

Also read: Who will be the next Himachal Pradesh CM? Congress to decide in key party meet today; check details

According to a 2018 order of the high court, there exists a "total freeze" on the destruction of mangroves across the state and permission has to be sought from the high court each time an authority wishes to fell mangroves for any public project.

"A 50 metre buffer zone must be created around the area that hosts the mangroves and no construction activity or dumping of debris can be permitted within this buffer zone," the order read. In its petition filed in 2020, the NHSRCL had assured the court it would plant five times the total mangrove trees that were earlier proposed to be felled and the number would not be reduced for the same.

Also read: TMC sends delegation to Gujarat as police re-arrest Saket Gokhale minutes after granted bail; check details

The plea was opposed by 'Bombay Environmental Action Group', an NGO, on the ground that no study was undertaken about the survival rate of saplings to be planted as a compensatory measure and the Environmental Impact Assessment report for felling trees has not been provided.

However, the NHSRCL had denied the objections raised by the NGO and claimed that it had availed required approvals for the felling of trees for the project of public importance and would compensate the loss occurring due to the same by planting of saplings as directed.

The 508-km high speed rail corridor between Ahmedabad and Mumbai is expected to cut travel time from six-and-a-half hours to two-and-a-half hours. The bullet train project received a major push after the Eknath Shinde-Bharatiya Janata Party (BJP) government came to power in June this year.