Namma Metro: New Metro Trains to Ease Heavy Crowding on Bengaluru Purple, Green Lines

Published : Feb 25, 2026, 02:22 PM IST

Commuters on Bengaluru's Namma Metro Purple and Green lines are facing severe crowding, with many unable to board trains during peak hours. Titagarh Rail Systems has dispatched first of several new trains, expected to undergo testing before service.

PREV
16
New Trains Set To Ease Crowding On Bengaluru Metro

Daily commuters on Namma Metro in Bengaluru are facing heavy crowding on the Purple and Green lines during peak hours. Many passengers have to wait for one or two trains to pass before they can board. The addition of three new trains is expected to give some relief on these busy routes.

26
First new train dispatched after delay

Titagarh Rail Systems Limited is building the new metro trains. After months of delay, the company dispatched its first DTG train on February 18. It is expected to reach the Peenya depot by the end of February. Once it arrives, workers will assemble its six coaches. The train will then undergo several tests, including a 750-kilometre night trial, before it is cleared for public service.

36
Background of the train supply contract

In 2019, CRRC Nanjing Puzhen won a ₹1,578 crore contract to supply 36 metro trains. The plan included 15 trains for the Yellow Line and 21 for the Purple and Green lines. However, only two prototype trains built in China were delivered. The remaining 34 trains are now being manufactured in India by Titagarh. The train dispatched on February 18 is the first among the 20 trains meant for the Purple and Green lines.

46
Different signalling systems for different lines

Trains for the Yellow Line will use a Communication-Based Train Control (CBTC) system, which allows driverless operations. But the new trains for the Purple and Green lines will use a DTG signalling system and will require loco pilots.

Even though a prototype train for the Purple Line arrived in January 2025, it is still waiting for 37 official approvals. Officials say all safety checks are complete except the multi-train anti-collision test. The signalling software is currently under testing.

56
Delivery timeline and expected relief

Titagarh plans to deliver the third DTG train by the end of March. After that, the company will focus on sending CBTC trains for the Yellow Line. Later, 18 more trains will be supplied for the Purple and Green lines.

Officials aim to have at least three new trains running on these crowded lines by May or June. They hope this will reduce congestion for daily commuters.

66
Rising passenger numbers driving demand

At present, 57 trains operate on the Purple and Green lines. However, this number is not enough to handle the growing passenger load. On weekdays, ridership has crossed 10 lakh passengers. Many commuters are now hoping the new trains will provide much-needed relief from daily overcrowding.

Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.

 