A newly constructed 18-storey apartment building in Bengaluru's Kudlu area, off Hosur Road, has developed a noticeable tilt just months after receiving an Occupancy Certificate (OC) from the Greater Bengaluru Authority (GBA). The incident has raised serious concerns about construction quality and structural safety, particularly as the building was cleared for occupation only in April this year.
Following the discovery, representatives of SNN Raj Developer met GBA Chief Commissioner Maheshwar Rao and other officials on Thursday to seek permission to demolish and reconstruct the affected tower. According to sources, the developer attributed the structural issue to errors in the pre-construction geotechnical investigation, commonly referred to as the soil investigation report.
The developer has sought the GBA's approval to demolish and reconstruct Wing E3 of the SNN Raj Eternia residential project from the foundation.
The project was originally approved for 143 flats and comprises three residential blocks, each with a basement, ground floor and 18 upper floors. The GBA issued the Occupancy Certificate for the completed building on April 30.
The issue came to light during the developer's final engineering inspection before the apartments were scheduled to be handed over to buyers.
During the inspection, engineers detected irregularities in the foundation of Wing E3, prompting the developer to carry out an emergency technical assessment to determine the extent of the problem.
According to the developer, the technical assessment found that the building had settled significantly more than expected.
Engineers also identified substantial differences between the original geotechnical investigation report and a fresh soil assessment conducted after the building developed the tilt. Based on these findings, the technical team concluded that Wing E3 was unsafe for occupation and recommended its demolition, sources said.
SNN Raj Developer has assured the authorities that the affected building will be demolished and reconstructed entirely at the company's expense to ensure the safety of homebuyers.
The developer also said it would maintain complete transparency throughout the demolition and reconstruction process.
According to the developer, the demolition, reconstruction and handover of the new building are expected to take approximately 18 to 20 months.
The Greater Bengaluru Authority is expected to issue an official demolition order shortly. According to sources, demolition of the 18-storey building could begin as early as next week, subject to the necessary approvals.
Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.