Vikramshila Setu: Bailey bridge work progresses fast to restore traffic

Published : May 25, 2026, 01:30 AM IST
Underconstruction Bailey Bridge (Photo/ANI)

Synopsis

Bailey bridge construction at Bhagalpur's Vikramshila Setu is progressing rapidly after a slab collapse. One of three single-lane bridges is launched, and a second is nearing completion, aiming to restore traffic on the crucial route soon.

Construction work on the Bailey bridges at Bhagalpur's Vikramshila Setu is progressing rapidly, with authorities aiming to restore traffic movement on the crucial route soon. The work is expected to bring relief to commuters after the bridge remained closed following the collapse of a slab earlier this month.

BRO Details Bridge Progress

According to Superintending Engineer of the Border Roads Organisation (BRO), Vipin Kumar Chand, one of the three planned Bailey bridges has already been fully launched, while the second is in the final stages of decking and finishing work. Preparations for the third bridge are also underway. Speaking to ANI, Chand said, "In total, three Bailey bridges are planned. Of these, one has been fully launched, while the second is now undergoing decking and finishing work. These smaller tasks will take two to three days to complete. Preparations for launching the third bridge have already begun. The bridges are single-lane. The administration will decide which types of vehicles are permitted to use the bridge. One bridge is complete, the second is nearing completion, and the third will follow the same process. We are making every effort to meet the deadline, as people are facing difficulties and delays. We aim to restore movement as quickly as possible."

Government Pledges Quick Reopening

Earlier, Bihar Public Works Department Minister Kumar Shailendra said repair work on the damaged Vikramshila Setu is progressing quickly, and the bridge is expected to become operational again within 10 to 15 days. After inspecting the site, Shailendra said the government took immediate action after a portion of the bridge collapsed earlier this month. "Immediately after this bridge collapsed, CM Samrat Choudhary, the Secretary, and I held a meeting. We prepared a detailed plan to fix it right away. We will have it operational again within 10 to 15 days," he said.

The minister added that repair work on the damaged sections is being carried out transparently.

Background of the Collapse

On May 3, a slab between two pillars of the Vikramshila Setu, which connects the Purvanchal region with Seemanchal across the Ganga river, collapsed. Following the incident, district officials and senior police officers rushed to the spot; traffic was halted, and routes were diverted.

According to reports, a 10-inch expansion joint first subsided, after which a slab near pier number 133 gave way and fell into the river. The bridge, a key link between Bhagalpur and Seemanchal, has remained closed to traffic since the incident. (ANI)

(Except for the headline, this story has not been edited by Asianet Newsable English staff and is published from a syndicated feed.)

PREV

Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Get real-time updates from IMD on major cities weather forecasts, including Rain alerts, Cyclone warnings, and temperature trends. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.

Recommended Stories

Uttarakhand: CEC reviews prep for intensive voter list revision
Amit Shah hails BJP's Falta win as mandate for progress in Bengal