Relief may soon be in sight for commuters battling daily traffic snarls at the busy Silk Board junction, as the city’s first double-decker flyover nears completion. The ₹449-crore infrastructure project, designed to ease chronic congestion at one of Bengaluru’s most notorious bottlenecks, is expected to become fully operational by the end of February, officials said.
While one side of the flyover was opened in 2024, progress on the remaining stretch was delayed due to the complex installation of a 42-metre steel bridge over the existing roadway. With most of the pending work now complete, commuters are hopeful of a smoother commute in the coming weeks.
Workers are currently completing the concrete slab work, and officials from the Bangalore Metro Rail Corporation Limited (BMRCL) said the civil works are targeted for completion by the end of February.
The flyover connects HSR Layout with BTM Layout and is expected to significantly improve traffic movement by allowing vehicles to bypass the Silk Board junction entirely.
The project faced delays mainly due to the installation of a massive 42-metre steel girder over existing infrastructure. With this critical component now in place, the remaining work has progressed rapidly, raising hopes for an early inauguration.
For daily commuters, the flyover promises much-needed relief. “I travel from Banashankari, and Silk Board is the worst part of my journey. Even a 10-minute reduction in waiting time would be a big help. Silk Board is a nightmare every evening. If this ramp opens, vehicles heading towards HSR and Hosur Road will move faster,” said a commuter.
Another commuter added, “Avoiding the signal from Silk Board to BTM Layout will be a huge relief.”
Once operational, the flyover will allow traffic to move uninterrupted between Silk Board, BTM Layout, HSR Layout and Hosur Road, significantly reducing congestion at the junction, officials said.
BMRCL officials said the project is in its final stage and will be opened after mandatory inspections.
“Once the contractor completes the final touches, the traffic police will inspect the structure before it is opened to the public,” a BMRCL official said.
DCP (Traffic, South) Gopal M. Byakod confirmed that the flyover is expected to be fully operational by the end of February, easing traffic flow from the Central Silk Board junction towards BTM Layout, HSR Layout and Bellandur.
Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.