Bengaluru Metro Pink Line: Railway Board Approves BEML Trains, October Launch Likely

Published : Sep 24, 2026, 03:30 PM IST
Bengaluru Metro Pink Line Gets Railway Board Approval For BEML Trains

Synopsis

Bengaluru Metro's Pink Line has received Railway Board approval for BEML-manufactured trains. BMRCL is targeting commercial operations on the elevated stretch by the second week of October, subject to CMRS safety clearance.

Bengaluru's metro network is set for a major expansion, with the Railway Board officially approving the operation of BEML-manufactured trains on the Pink Line. The approval marks a crucial step towards the commercial launch of the elevated section, with the Bangalore Metro Rail Corporation Limited (BMRCL) aiming to begin operations by the second week of October, subject to the required safety clearance. Once operational, commuters are expected to have a train every six minutes during peak hours and every 10 minutes during non-peak hours.

BMRCL received the Railway Board's approval today and will now submit the approval, along with the necessary documents, to the Commissioner of Metro Railway Safety (CMRS). This development brings the Pink Line closer to commercial operations. The entire Pink Line connects Kalena Agrahara to Nagawara and covers 21.26 km, comprising a 13.76 km underground stretch and a 7.5 km elevated corridor. BMRCL plans to open the line in two phases.

The elevated section of the Pink Line runs from Kalena Agrahara to Tavarekere and has six stations: Kalena Agrahara, Hulimavu, JP Nagar 4th Phase, IIMB, Jayadeva Hospital and Tavarekere. Once this stretch becomes operational, Bengaluru Metro's total operational network will increase to 103.6 km.

A Six-Month Wait Finally Ends

The launch of the Pink Line has been awaited for around six months, with the delay largely linked to statutory approvals required for the trains. BMRCL plans to deploy six trains initially on the 7.5 km elevated stretch. The metro corporation has also recently completed signalling tests and secured the required certification.

CMRS Inspection Is The Final Hurdle

BMRCL officials recently met V. Venkatasubramanian, the Commissioner of Metro Railway Safety for the Southern Circle, and submitted several documents related to the upcoming safety inspection. The CMRS has sought a comprehensive set of records before beginning the physical inspection.

The CMRS team is expected to conduct a detailed two-day inspection of the Kothanur depot, the six stations along Bannerghatta Road, the viaduct and tracks, and other systems using a motor trolley.

The Pink Line can begin commercial operations once the CMRS grants the final safety clearance. Earlier, French company Alstom submitted a report on the signalling system. Based on the report, Bengaluru-based Jodova Technologies issued an Independent Safety Assessment (ISA) certificate, confirming the safety of the signalling system and its technical interfaces.

The CMRS team had also inspected the imported trains earmarked for the line between August 12 and August 14 as part of the safety assessment process.

PREV

Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.

 

Read more
Read more Articles on

Recommended Stories

Arasikere Railway Station: Vande Bharat Stop, MEMU Train Demands Raised
Cyclone Arnab: Will Karnataka Get Heavy Rain? Check IMD Warning Here