NHSRCL refutes claims on bullet train cost, calls it 'conjecture'

Published : Mar 05, 2026, 08:30 PM IST
Installation of overhead electrification masts is progressing well on the Mumbai–Ahmedabad Bullet Train project (File Photo/X@AshwiniVaishnaw)

Synopsis

The National High-Speed Rail Corporation Limited has rejected claims by the Kerala Congress regarding the financial status of the Mumbai-Ahmedabad Bullet Train project, calling them 'conjecture', 'selective interpretation' and 'factually wrong'.

The National High-Speed Rail Corporation Limited (NHSRCL) has officially rejected claims regarding the financial status of the Mumbai-Ahmedabad Bullet Train project, stating, "The commentary circulating on the Mumbai-Ahmedabad High Speed Rail Project relies largely on conjecture and selective interpretation rather than verified facts. Several of the claims made are factually wrong."

Clarification on Project Cost Estimates

The corporation clarified that "updated project cost estimates are comparable to global benchmarks" and explained that "the initial estimate was prepared at a preliminary stage nearly a decade ago. As is standard practice in major infrastructure projects worldwide, costs are refined once detailed design, engineering, land acquisition and construction contracts are finalised."

Dispute Over Cost Escalation and Funding

This point-by-point clarification was issued by the NHSRCL in response to a critical social media post by the Kerala unit of the Congress party. The opposition party had earlier posted on X, "As we exposed nearly two years ago, Modi's vanity project, the Mumbai-Ahmedabad Bullet Train, has seen its cost escalate from the original Rs 1.1 lakh crore to Rs 1.98 lakh crore. This is when the project is half complete. The final cost could be more than 2.5 lakh Cr."

Regarding the funding of this increase, the Kerala Congress said, "The additional Rs 90,000 crore burden will now be borne by Indian Railways, which is already struggling for funds. The Japanese agency JICA is not going to fund this escalation."

NHSRCL Rebuts Funding Burden Claim

In its response, the NHSRCL countered this by saying, "It is also incorrect to state that the burden is being placed on Indian Railways. The project is implemented through the dedicated entity National High Speed Rail Corporation Limited, which has its own financing structure."

Financial Agreements and Interest Rate Speculation

The opposition further alleged a shift in debt interest rates, stating, "The main attraction of JICA funding was the ultra-low 0.25% interest rate. But this extra Rs 90,000 crore will now be raised as debt by the Government of India at 7-8% interest. It will take more than a century to recover the cost."

Addressing the financial agreements, the NHSRCL noted, "The agreement between India and Japan for funding the project is comprehensive, and the speculations made have no base." The corporation added that the project continues to be "backed by one of the most concessional sovereign loans ever extended for infrastructure, with extremely low interest and long repayment periods."

Future Ticket Prices and Economic Impact

Finally, the Kerala Congress raised concerns about the impact on the public, writing, "The original projected ticket price between Mumbai and Ahmedabad was around ₹3,000. With costs nearly doubling while the project is only half complete, ticket prices could well touch Rs 6,000-Rs 7,000."

The NHSRCL dismissed these figures, stating, "Ticket pricing will be affordable. The speculative numbers have no basis and are meant to mislead people." The agency concluded by emphasising that high-speed rail generates value through "time savings and productivity gains" and "regional economic development along the corridor." (ANI)

(Except for the headline, this story has not been edited by Asianet Newsable English staff and is published from a syndicated feed.)

PREV

Stay updated with all the latest Business News, including market trends, Share Market News, stock updates, taxation, IPOs, banking, finance, real estate, savings, and investments. Track daily Gold Price changes, updates on DA Hike, and the latest developments on the 8th Pay Commission. Get in-depth analysis, expert opinions, and real-time updates to make informed financial decisions. Download the Asianet News Official App from the Android Play Store and iPhone App Store to stay ahead in business.

 

Recommended Stories

India's GDP at risk as crude oil prices spike amid gulf tensions
EaseMyTrip founder Nishant Pitti named 'Most Influential Entrepreneur'