Mumbai-Ahmedabad Bullet Train: Breakthrough in third mountain tunnel

Published : Jun 02, 2026, 01:30 PM IST
3rd mountain tunnel in Palghar District (Photo/NHSRCL)

Synopsis

A breakthrough has been achieved in the 417-metre-long third mountain tunnel for the Mumbai-Ahmedabad Bullet Train in Palghar, Maharashtra. This marks the third tunnel excavation in five months, showcasing rapid progress on the project.

The breakthrough in the third mountain tunnel in Maharashtra has been achieved for the Mumbai-Ahmedabad Bullet Train Project at Ambesari village in Dahanu Taluka of Palghar district. The tunnel is 417 metres long and 14.4 metres wide, designed to accommodate both up and down tracks of the Bullet Train corridor.

Excavation and Safety Measures

The excavation was carried out using the controlled drilling and blasting method from both ends. Advanced monitoring systems and geotechnical instruments were deployed throughout the excavation process to ensure structural stability and safety.

Real-time monitoring systems, including Surface Settlement Points (SSP), 3D targets, strain gauges, and seismographs, were installed for continuous monitoring of vibrations, tunnel behaviour, and nearby structures during excavation activities.

Special emphasis was given to worker safety inside the tunnel through proper ventilation systems, fire safety measures, controlled access arrangements, and continuous geotechnical monitoring.

Project Tunnel Overview

Out of the total eight (08) mountain tunnels in the project, seven (07) are located in Palghar district of Maharashtra and one (01) in Valsad district of Gujarat.

Completed Tunnels

Work is moving ahead quickly, with four tunnels already fully dug out: MT-08 (350 metres): Completed on October 5, 2023, MT-05 (1.5 kilometres): Completed on January 2, 2026, MT-06 (454 metres): completed on February 3, 2026 and MT-07 (417 metres): completed on June 1, 2026.

Tunnels Under Construction

The remaining four tunnels are actively under construction, such as MT-04: nearly 60% of the digging work is finished, MT-03: More than 80% of the excavation is complete, and MT-02 and MT-01: excavation work is moving forward at a steady pace.

With the excavation of this mountain tunnel, three mountain tunnels have been excavated within the last 5 months in Maharashtra, marking rapid progress in one of the most complex sections of the project.

Vapi-Boisar Section Progress

All three mountain tunnels between Vapi and Boisar Bullet Train stations have been successfully excavated. The Mumbai-Ahmedabad Bullet Train corridor passes through an important industrial region between Boisar in Maharashtra and Vapi in Gujarat, where construction work is progressing rapidly. The route between these two cities includes three (03) mountain tunnels (MT 08, MT-07 & MT-06). (ANI)

(Except for the headline, this story has not been edited by Asianet Newsable English staff and is published from a syndicated feed.)

PREV

Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Get real-time updates from IMD on major cities weather forecasts, including Rain alerts, Cyclone warnings, and temperature trends. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.

Recommended Stories

NEET Irregularities: A betrayal of a generation, says Shashi Tharoor
Uttarakhand: Car plunges into gorge in Tehri, another kills 2