Air Marshal Dixit reviews LCA Tejas Mk1A progress at HAL Bengaluru

Published : Jun 13, 2026, 01:00 PM IST
Ashutosh Dixit, Air Marshal, (CISC), (PHOTO/X/@HQ_IDS_India)

Synopsis

Air Marshal Ashutosh Dixit reviewed the LCA Tejas Mk1A programme at HAL, Bengaluru. Officials are confident of delivering the jets this financial year despite delays caused by engine supply disruptions and pending weapon system integration.

Air Marshal Ashutosh Dixit, Chief of Integrated Defence Staff to the Chairman Chiefs of Staff Committee (CISC), visited Hindustan Aeronautics Limited's (HAL) Aircraft Division in Bengaluru and reviewed the progress of the Light Combat Aircraft (LCA) Tejas Mk1A programme, along with other key indigenous aviation projects.

During the visit, Air Marshal Dixit assessed the status of the Tejas Mk1A programme, a key pillar of the Indian Air Force's modernisation efforts and one of India's flagship indigenous defence initiatives. The senior officer was also briefed on the progress of other important aerospace programmes, including the Hindustan Turbo Trainer (HTT)-40, the country's indigenous basic trainer aircraft developed to meet pilot training requirements.

Delivery Expected This Financial Year Amid Delays

Secretary of Defence Production, Sanjeev Kumar, earlier in an interview to ANI, expressed confidence in the Indian Air Force receiving the Tejas Mark 1A fighter jets from Hindustan Aeronautics Limited (HAL) in the current financial year after the delays in the supply.

The Indian Air Force has ordered 180 of these aircraft in two tranches, but deliveries have been delayed. The planes were likely to be delivered last year, but the Indian Air Force has insisted that HAL provide the aircraft in a fully operational configuration.

HAL conducted the first flight of the first Tejas Mk1A prototype from its Nashik facility on October 17, 2025.

In an interview with ANI, Sanjeev Kumar acknowledged the delays in supplying the fighter jet, stating that the product is about 90 per cent ready. While suggesting HAL do due diligence, Kumar also attributed the delays in the supply of Tejas Mark 1A to a delay in receiving the engines from the American firm GE Aerospace. Answering a query regarding the Tejas Mk1A being delivered in the current financial year, he said, "I am 100 per cent confident... The remaining five to ten per cent, a small part of the development, which is the integration of certain weapons, is almost done, but still not fully done.

Probing the Reasons for Delay

When asked about "hand-holding" companies manufacturing in the defence sector, Kumar said, "Hand-holding is necessary to any industry which is coming into the defensive manufacturing system. Hand-holding, to the extent possible it should be done. But, no long rope should be given. Every participant should be aware of their responsibility, and they should try hard to meet the commitment which has been given. While agreeing totally that yes, there is a delay, we need to understand how we can reduce these delays in future projects or even this project. So there is the role of understanding the reasons for delay and then working on those reasons so that in future it doesn't become a bottleneck, it doesn't become a weak point in our ecosystem. "

Noting the causes for the delay, the Secretary of Defence Production said that the HAL, DRDO and the Air Force are holding discussions to enable a faster supply in the future. He said, "There are two types of systems. One is a system which is being developed and would be delivered. Second is an already developed system, which is going to be manufactured and delivered. Since we are in that stage of development, development and delivery both go hand in hand. And in the case of LCA, we see that this Tejas Mark 1A and afterwards Mark 2, also would be coming in, are being developed even now. DRDO is in charge of a certain part of it. We are integrating certain weapon systems and radar to the satisfaction of the purchaser. Secondly, many of the components of LCRs come from the outside, like the G4041 engine and the radar. "

90 per cent of the product has been created, but 10 per cent remains. I am just giving a number, which does not mean 90-10. Second, part of the critical component is coming from somewhere else. So, while the reasons for delay are certainly with the company who are supposed to deliver, they should have done due diligence, should have created more choices. Part of the reason is that this is still a project which is under development. A healthy discussion is going on, and I am sure HAL and Air Force and DRDO and HAL or the suppliers would come out with better solutions and should be able to supply faster in future," he added.

He stated that the delay in delivering the jet engines was due to a disrupted supply chain and the COVID-19 pandemic. Kumar told ANI, "What seems plausible is that the 404 supply chain got disrupted because of a lack of orders from others to GE and secondly, because of COVID. And certainly, that supply chain, after getting disrupted, is taking time. Secondly, I believe that there is a huge stress on many of the factories on various types of jet engine requirements, because the civil aviation side of the business also requires a large number of jet engines. "

Domestic Needs Prioritised Over Exports

Further, he said that India has received inquiries from foreign nations for purchasing Tejas; however, New Delhi has made a strategic choice to meet the Indian Air Force's needs first. "Brahmos and Pinaka's advanced talk is going on. So there's a good demand, and an artillery system also. For Tejas also, many talks is going on with many countries. First, we have to satisfy our own needs. There are good, credible inquiries from foreign countries which believe in the capability of Tejas. But it is our strategic choice. First, we will meet our own requirement, then only we will start supplying," he said.

In April this year, HAL's Chief Managing Director, DK Sunil, had said that there were delays in receiving the software for India's flagship fighter program, Tejas, amid the West Asia conflict. (ANI)

(Except for the headline, this story has not been edited by Asianet Newsable English staff and is published from a syndicated feed.)

PREV

Stay updated with the Breaking News Today and Latest News from across India and around the world. Get real-time updates, in-depth analysis, and comprehensive coverage of India News, World News, Indian Defence News, Kerala News, and Karnataka News. From politics to current affairs, follow every major story as it unfolds. Get real-time updates from IMD on major cities weather forecasts, including Rain alerts, Cyclone warnings, and temperature trends. Download the Asianet News Official App from the Android Play Store and iPhone App Store for accurate and timely news updates anytime, anywhere.

Recommended Stories

Indian sailors are safe, attack report is fake news: Seamen's Union
Sabarimala gold theft accused Murari Babu dies of cancer in Kochi