Bullet Train: 5 Heavy Portal Beams Installed Over Tracks in Ahmedabad

Published : May 04, 2026, 07:30 PM IST
Five portal beams installed over Ahmedabad railway tracks (Photo/ANI)

Synopsis

The Mumbai-Ahmedabad bullet train project achieved a key engineering milestone by installing five heavy portal beams, weighing up to 1360 metric tonnes, over active Indian Railways tracks at Maninagar, Ahmedabad, within just 22 days in April 2026.

The Mumbai-Ahmedabad bullet train project has completed the installation of five heavy portal beams over active Indian Railways tracks at Maninagar in Ahmedabad within 22 days, marking a key engineering milestone.

Details of the Operation

According to an official release, all five precast-prestressed portal beams were launched over the Ahmedabad-Vadodara railway line in a phased manner on 8th, 13th, 19th, 24th and 29th April 2026, in close coordination with Indian Railways. The operation involved the installation of beams weighing between 1170 metric tonnes and 1360 metric tonnes. The heaviest beam, weighing around 1360 metric tonnes, was launched on April 8, making it one of the heaviest lifts carried out on operational railway tracks in the country.

Overcoming Engineering Hurdles

The work was executed on active railway lines, including the Ahmedabad-Vadodara 'Up', 'Down' and third lines, requiring a high level of planning, coordination and safety measures. The alignment at Maninagar passes above existing railway tracks at a raised level with limited space and a span of approximately 30 to 34 metres between piers, necessitating the use of heavy portal beam structures.

Advanced Technology and Execution

These portal beams are designed to provide strong and rigid support to safely transfer loads across multiple tracks, ensuring minimal deflection and maintaining precise track alignment for safe railway operations. The launching was carried out using a 2200 metric-ton crawler crane, marking its first use on Indian railway tracks. Each beam was installed in approximately 3.5 hours, significantly reducing the time compared to earlier operations that required up to nine-hour blocks. Despite challenges such as limited working space, overhead electrification (OHE), and ongoing train movement, the installation was completed with continuous monitoring and safety checks.

A portal beam is a precast concrete structure measuring 34 metres in length, with a cross-section of 5.5 metres by 4.5 metres, and is installed as an integrated unit to support elevated infrastructure over railway lines. (ANI)

(Except for the headline, this story has not been edited by Asianet Newsable English staff and is published from a syndicated feed.)

PREV

Stay updated with all the latest Business News, including market trends, Share Market News, stock updates, taxation, IPOs, banking, finance, real estate, savings, and investments. Track daily Gold Price changes, updates on DA Hike, and the latest developments on the 8th Pay Commission. Get in-depth analysis, expert opinions, and real-time updates to make informed financial decisions. Download the Asianet News Official App from the Android Play Store and iPhone App Store to stay ahead in business.

 

Recommended Stories

Govt assures stable fuel, LPG supply; no immediate price hike plans
IMC Report Outlines Roadmap to Boost India's Corporate Bond Market